The Ohio Court of Appeals has issued a ruling in a construction contract dispute involving Suburban Maintenance and Construction, Inc. and Complete General Construction Company. The court affirmed the lower court's decisions, which favored Complete General, impacting how subcontractors may pursue claims against general contractors in similar situations.

This case, Suburban Maintenance & Constr., Inc. v. Complete Gen. Constr. Co., No. 25AP-454, stems from a disagreement over a construction project involving the replacement of a railroad bridge in Columbus, Ohio. The court's ruling clarifies important aspects of contract law and the obligations of subcontractors when claims are made.

Background

Suburban Maintenance, the plaintiff-appellant, entered into a subcontract with Complete General Construction, the defendant-appellee, to perform specific work on the railroad bridge project. The City of Columbus owned the project and had a separate contract with Complete General. Suburban was responsible for drilling and placing concrete for 34 shafts that would support the bridge.

The dispute arose when Suburban claimed that Complete General caused delays and disruptions that warranted additional compensation. On January 3, 2020, Suburban filed a complaint against Complete General, alleging breach of contract and seeking damages. Complete General responded with counterclaims, arguing that Suburban's claims were barred due to prior rejections by the City, which were part of the contract's dispute-resolution process.

The case progressed through the Franklin County Court of Common Pleas, where the trial court granted summary judgment in favor of Complete General on December 5, 2023. This ruling concluded that Suburban's claims were effectively barred because they had not followed the required dispute-resolution process outlined in their subcontract.

The Ruling

The Ohio Court of Appeals affirmed the trial court's decisions in a ruling issued on October 22, 2026. The court upheld the summary judgment that dismissed Suburban's claims, stating, "the claim-resolution process set forth in the Principal Contract...was Suburban’s exclusive remedy with regard to its claims." This decision emphasized that Suburban's failure to pursue the claims through the designated channels barred them from seeking relief in court.

Furthermore, the court addressed Complete General's counterclaims, which were resolved in favor of Suburban by a magistrate's decision. The magistrate found that General's claims for misrepresentation and breach of contract were without merit, as Suburban's alleged production rates were not enforceable contractual provisions. The magistrate stated that General did not prove damages with sufficient certainty, leading to a dismissal of their claims.

Impact

This ruling has significant implications for subcontractors and general contractors in Ohio. It reinforces the importance of adhering to contractual dispute-resolution processes, especially in construction contracts where multiple parties are involved. Subcontractors must ensure they follow the agreed-upon procedures for claims to avoid being barred from recovery.

Additionally, the court's decision clarifies that claims based on misrepresentation must meet specific legal standards, particularly regarding the nature of the statements made. This ruling may deter subcontractors from pursuing claims based on vague or unproven assertions about production rates or timelines.

What's Next

Suburban Maintenance has the option to appeal the ruling to the Ohio Supreme Court, although it is unclear if they will pursue this route. The case sets a precedent for future construction contract disputes, emphasizing the need for clear communication and adherence to contractual obligations.