The Armed Services Board of Contract Appeals recently ruled on a significant appeal from Hensel Phelps Construction Company regarding a construction project for the U.S. Army Corps of Engineers. The court decided to deny the government's motion to dismiss the delay portion of Hensel Phelps' appeal, which seeks over $22 million for costs related to delays in the construction of the Bureau of Engraving and Printing Western Currency Facility Expansion Project in Fort Worth, Texas.

This ruling is crucial as it allows Hensel Phelps to continue pursuing compensation for delays they claim were caused by inadequate government-provided designs. The case underscores the complexities of construction contracts and the importance of clear communication and documentation in government projects.

Background

Hensel Phelps Construction Company, a major player in the construction industry, was awarded Contract No. W9126G-18-C-0061 by the U.S. Army Corps of Engineers on September 20, 2018. This contract involved the construction of the Bureau of Engraving and Printing Western Currency Facility Expansion Project. After completing the project, Hensel Phelps filed a certified claim seeking $22,050,672 for various costs associated with delays, including general conditions and other direct costs.

The dispute centers on Hensel Phelps' assertion that the delays were primarily due to a “seriously deficient and inadequate” design provided by the government, which led to extensive requests for information and proposals. The company claimed that the design flaws necessitated over 2,200 requests for information, resulting in significant disruptions and delays across multiple contract line items. Hensel Phelps argued that these issues prevented them from completing various aspects of the project independently.

After the U.S. Army Corps of Engineers acknowledged 190 days of government-caused delay, they deemed these delays non-compensable due to concurrent delays. This led to Hensel Phelps filing an appeal with the Armed Services Board of Contract Appeals, seeking to recover costs related to the additional delays they experienced.

The Ruling

The court, led by Administrative Judge Thomas P. McLish, ruled against the government's motion to dismiss the delay portion of Hensel Phelps' appeal. The government had argued that Hensel Phelps failed to meet the “sum certain” requirement for a valid claim, suggesting that the delay claim consisted of multiple distinct claims that each required a specific monetary amount.

The court stated, "Hensel Phelps has adequately stated a claim for which relief may be granted. The government’s motion is denied."

The ruling emphasized that the government did not demonstrate that Hensel Phelps' delay claim was made up of multiple distinct claims, and the court found that the delays and additional costs suffered by Hensel Phelps were due to a common set of operative facts related to the alleged deficiencies in the government’s design.

Impact

This ruling allows Hensel Phelps to proceed with their appeal, which could have significant financial implications for the company. If the board ultimately rules in favor of Hensel Phelps, it could set a precedent for how similar claims are handled in the future, particularly regarding the interpretation of the “sum certain” requirement in construction contracts with the government.

The decision also highlights the importance of thorough documentation and clear communication in government contracts, as disputes over design deficiencies and delays can lead to costly legal battles. The outcome of this case may influence how contractors approach claims related to project delays and the documentation they provide to support their claims.

What's Next

Hensel Phelps can continue to pursue their appeal following this ruling. There is no indication that the government plans to appeal this decision, but the case may still face further legal challenges as it progresses through the appeals process.