The Puerto Rico Court of Appeals recently reversed a lower court's decision that ordered property owners to demolish unauthorized construction on their property in Bayamón. This ruling, which affects Sobeida de los Ángeles Blanco Martínez and Adán Christian Montalvo López, highlights significant issues regarding property rights and due process in legal proceedings.

The case, El Gobierno Municipal Autónomo De Bayamón v. Sobeida De Los Ángeles Blanco Martínez, Adán Christian Montalvo López Y Otros, was filed on May 13, 2026, under docket number TA2026AP00427. The dispute arose when the local government claimed that the defendants had constructed an apartment without the necessary permits and installed windows that violated local regulations.

The Government of Bayamón initiated the legal action on January 3, 2026, seeking a statutory injunction against Blanco Martínez and Montalvo López. The municipality argued that the construction work was unauthorized and requested the court to order the demolition of the apartment, restore the property to its original state, cease the apartment's use, and remove improperly installed windows. The municipality also sought reimbursement for legal fees.

The case progressed through the court system, with hearings scheduled and rescheduled due to various circumstances, including the absence of one of the defendants. On March 25, 2026, the lower court held a hearing where the municipality presented its case, but the defendants did not provide evidence. Subsequently, on March 27, 2026, the lower court issued a permanent injunction against the defendants, ordering them to demolish the unauthorized construction and pay $1,000 in legal fees.

In response to this ruling, Montalvo López filed an appeal on April 27, 2026, asserting multiple errors in the lower court's decision. The appeals court, led by Judge Martínez Cordero, reviewed the case and found that the lower court had erred in several critical areas.

One of the key findings by the appeals court was that the lower court had failed to provide adequate notice to Blanco Martínez regarding the proceedings. The court stated, "the incorrect notification atenta contra los derechos de las partes, al privarles de cuestionar el dictamen emitido y causarles demoras e impedimentos en el proceso." This means that the lack of proper notification violated the defendants' rights to due process, as they were not given a fair opportunity to defend themselves in court.

The appeals court also highlighted that the lower court had incorrectly treated Blanco Martínez and Montalvo López as having the same legal representation, which led to further procedural errors. The court noted that Montalvo López's attorney did not represent Blanco Martínez, and as a result, she was not adequately represented during the proceedings.

As a result of these findings, the Court of Appeals reversed the lower court's decision and ordered the case to be sent back for further proceedings. The court mandated that Blanco Martínez be properly notified of all future proceedings and that the case be rescheduled promptly to ensure justice is served.

This ruling has significant implications for property owners in Puerto Rico, particularly regarding the enforcement of local regulations and the importance of due process in legal proceedings. It underscores the necessity for courts to adhere to proper notification procedures to ensure that all parties have the opportunity to defend their rights adequately.

The appeals court's decision may set a precedent for future cases involving property disputes and due process rights. It emphasizes the importance of legal representation and the need for courts to uphold the rights of all parties involved in legal proceedings.

Looking ahead, the case may still face additional legal challenges. The municipality could potentially seek to appeal the Court of Appeals' ruling to a higher court, although details about any such plans were not available in the court filing. Meanwhile, the case will return to the lower court for further proceedings, where the issues surrounding the unauthorized construction will be addressed anew.